$40$ persons can take $30$ days to complete a work. How long will it take if $20$ more people join them?
Answer
584.1k+ views
Hint: The given questions revolve around the concepts of proportions. There are mainly two types of relations between any two given variables: direct relation or direct proportion and inverse relation or inverse proportion. The given question is an illustration where a certain number of people take a specific number of days to complete a work and we have to calculate the number of days they will take if some more people join in. We first find out the type of relation or proportion in the number of days and the number of workers and then form a table of values for the same.
Complete step-by-step solution:
In the given problem,
Number of people initially is $40$.
So, the number of days taken to complete a work is $30$ days.
Now, we are given that $20$ more people join them and we have to calculate the number of days they will take in the new case.
So, let the number of days taken in the new case be x days.
Now, we know that if the number of workers increases, they will take less number of days to complete the same work and vice versa.
Hence, we know that the number of workers and the number of days they take to complete the work are indirectly proportional to each other.
Now,
So, making a table for the number of workers and the time taken by them to complete the work, we get,
Now, calculating the value of x following the inverse relation between the number of workers and the time taken by them to complete the task, we get,
$ \Rightarrow x = \dfrac{{40 \times 30}}{{60}}$
Carrying out the calculations in numerator, we get,
$ \Rightarrow x = \dfrac{{1200}}{{60}}$
Cancelling the common factors in numerator and denominator, we get,
$ \Rightarrow x = 20$
So, the time taken by workers if $20$ more people join in to complete the work is $20$ days.
Note: In any inverse proportion relation, the product of the two quantities remains constant. So, here, the product of number of workers and time duration remains constant in both the cases.
Complete step-by-step solution:
In the given problem,
Number of people initially is $40$.
So, the number of days taken to complete a work is $30$ days.
Now, we are given that $20$ more people join them and we have to calculate the number of days they will take in the new case.
So, let the number of days taken in the new case be x days.
Now, we know that if the number of workers increases, they will take less number of days to complete the same work and vice versa.
Hence, we know that the number of workers and the number of days they take to complete the work are indirectly proportional to each other.
Now,
So, making a table for the number of workers and the time taken by them to complete the work, we get,
| Number of workers | Time duration |
| $40$ | $30$ days |
| $60$ | x days |
Now, calculating the value of x following the inverse relation between the number of workers and the time taken by them to complete the task, we get,
$ \Rightarrow x = \dfrac{{40 \times 30}}{{60}}$
Carrying out the calculations in numerator, we get,
$ \Rightarrow x = \dfrac{{1200}}{{60}}$
Cancelling the common factors in numerator and denominator, we get,
$ \Rightarrow x = 20$
So, the time taken by workers if $20$ more people join in to complete the work is $20$ days.
Note: In any inverse proportion relation, the product of the two quantities remains constant. So, here, the product of number of workers and time duration remains constant in both the cases.
Recently Updated Pages
Find the greatest six digit number that is exactly class 8 maths CBSE

What is the time difference between India and Cana class 8 social science CBSE

Compare LPG and wood as fuels class 8 chemistry CBSE

In Indian rupees 1 trillion is equal to how many c class 8 maths CBSE

30 opposite words in English from a to z class 8 english CBSE

How many cubic feet equals to 1 unit sand class 8 maths CBSE

Trending doubts
What is BLO What is the full form of BLO class 8 social science CBSE

Citizens of India can vote at the age of A 18 years class 8 social science CBSE

Full form of STD, ISD and PCO

One cusec is equal to how many liters class 8 maths CBSE

Who commanded the Hector the first British trading class 8 social science CBSE

What are the methods of reducing friction. Explain